fbpx

New Immigration depot in Jawi set to complete in July

immigration-depot-jawi

Source: Malay Mail

The construction of the Jawi Immigration Detention Depot and Quarters, which was delayed for five years, has now reached 98 percent progress and is expected to be fully completed by the end of July.

Deputy Works Minister Datuk Seri Ahmad Maslan said the construction of the RM77.5 million project on a six-hectare plot began on May 27, 2019 and was supposed to be completed on May 8, 2022, but was given three delays following the Movement Control Order when the COVID-19 pandemic hit.

“This was an open tender project under the Public Works Department (JKR) as the implementing agency. It is expected to be completed on July 28,” he said after reviewing the project’s progress yesterday, with Penang Immigration director Nur Zulfa Ibrahim also present.

The project also includes the construction of a pump house and a suction tank as well as a two-kilometre-long water reticulation line to the depot to overcome the issue of low water pressure in the Jawi area, which has been affecting the water supply to the prison area and Taman Widuri.

“This project costs RM5.78 million, also through an open tender, with the total amount for both projects being RM83.28 million,” he said.

Ahmad said the construction of the depot is a project under the First Rolling Plan of the 11th Malaysia Plan, under the Home Ministry and belongs to the Penang Immigration Department, which aims to provide a conducive detention centre for illegal immigrants with enhanced security features.

Additionally, the project includes housing quarters for immigration officers, which will improve the readiness of officers to respond quickly to any disturbances in the detention blocks.

“This project will replace the existing Juru Immigration Detention Depot, built in 1976, which is now dilapidated and unsuitable for occupancy.

“On average, the Juru depot has a capacity for 500 detainees (350 men and 150 women). However, that capacity can be augmented with the completion of this new depot, which can accommodate some 1,200 detainees (834 men and 324 women),” he said.

Ahmad said JKR remains committed to ensuring that projects given by the ministry are completed on schedule or earlier.

Source: Bernama

RELATED PROPERTIES FOR SALE/RENT AT
  1. No comments yet.
(You can also Login/Register to submit your comment using unique ID)


Comment Guidelines
  • Avoid political discussion.
  • Comments with inappropriate wordings or personal attack may be moderated or deleted.
  • Developer must register before comment. All anonymous comments claimed to be from developer without registration will be deleted.
  • All advertisement in the comment will be deleted. Please contact us for advertising details.



To advertise your property in this page under "Related Properties for Sale/Rent":
 1. Submit your property at PenangPropertySale.com, it's FREE!
 (Please do not advertise your property in the comment)