fbpx

Ayer Itam-LCE Expressway bypass work to begin in October

Property News/ 28 August 2019 Leave a comment

ayer-itam-lce-expressway-pairroad

The first phase of Penang’s RM6.34bil tunnel and roads projects is set to kickstart construction by end-October 2019, amid criticism on the project’s cost and the delay in completing the feasibility study.

Consortium Zenith Construction Sdn Bhd, which is the main contractor for the multi-billion-ringgit project, has clarified that a master agreement was signed on Aug 2 that indicated the Penang state government’s commitment to proceed with the construction of the infrastructure works.

The RM6.34bil project – owned by the Penang state government – will consist of three toll-free roads and a tolled tunnel. The first phase of the project is the 5.7-km Ayer Itam-Lebuhraya Tun Dr Lim Chong Eu bypass. The cost of the first out of three roads, where construction would start in October, is estimated at RM1.07bil.

Consortium Zenith chairman Tan Sri Azmi Khalid told StarBiz that a land acquisition agreement would be signed on Aug 31 between the company and the Penang state government.

“The first phase, or what we call Package 2, is targeted to commence on or before Oct 31 this year. The construction period is 36 months from commencement.

“The construction cost of the Ayer Itam-Lebuhraya Tun Dr Lim Chong Eu bypass will be RM851.04mil and the land acquisition will cost another RM220mil. So, that makes RM1.07bil in total.

“One year after the first phase has started, we will begin with the next phase, ” he said.

Azmi said there has been a misunderstanding on the progress of the feasibility study.

“The feasibility study for the three major roads was completed on Jan 26,2016 and the approval for the Detailed Environmental Impact Assessment was received on Nov 7,2017.

“As far as the three roads are concerned, the approvals are all settled. This is why we have received a payment of RM208mil from the total of RM305mil in the form of 5.67 acres of reclaimed land.

“What is still pending is the feasibility study for the undersea tunnel, which is only about 10% left. A major reason for the delay is because we were asked by the Penang state government to put the feasibility study on hold for more than a year, as they were negotiating with the-then Barisan Nasional federal government on whether to build a bridge instead of an undersea tunnel, ” he said.

Azmi also pointed out that another reason for the delay in completing the feasibility study was the slower pace in finishing the land reclamation, which will be used to pay Consortium Zenith.

“Going by the agreement, Consortium Zenith will receive 110 acres of reclaimed land progressively and a toll concession for the tunnel as payment for our role in the entire project. This includes payment for the feasibility study.

“Earlier, there was a delay in land reclamation and the land was not ready to pay us for the work, ” stated Azmi.

For context, the Penang state government will pay for the RM6.34bil project via a land swap of 110 acres of reclaimed land in Tanjung Pinang, and a toll concession for the tunnel of not less than 30 years.

The exchanged land has been valued at RM1,300 per square foot based on net developed area.

Of the total RM6.34bil price tag, a total of RM305mil is estimated for the feasibility study and detailed design, RM546mil for land acquisition and RM5.49bil for construction.

For the development of the first phase of the project, Consortium Zenith will receive 29.1 acres of land.

Source: TheStar.com.my

Ayer Itam – LCE Expressway bypass

 

 

Tags:
RELATED PROPERTIES FOR SALE/RENT AT
  1. Internation
    August 28th, 2019 at 17:15 | #1

    Story again ? Announcement in April declared the dateline would be 31 Aug but now Nov ?
    After Nov then will be 2020, 2022 or even 2030 ?

  2. Gabriel
    August 28th, 2019 at 18:15 | #2

    The most expensive road work in Malaysia history.
    Suspected corruption. But, as long as my beloved party DAP can profit and survive with that money, I’m ok with it.

  3. tahusamatahu
    August 29th, 2019 at 20:29 | #3

    Why package 2 starts first over package 1 and not the other way round ? Fishy oh fishy ?

(You can also Login/Register to submit your comment using unique ID)

COMMENT GUIDELINES

  • Respectful Conduct: All comments must be respectful. Abusive, offensive, misleading or inappropriate language will be removed.
  • Relevance: Political or off-topic comments may be removed.
  • No Spam or Self-Promotion: Comments that are promotional or appear to be spam will be removed. Please refrain from sharing links or contact information in the comment.
  • Moderation: We reserve the right to review, edit, or delete any comments that violate these guidelines.
  • All advertisement in the comment will be removed. Please contact us for advertising opportunities.



To advertise your property in this page under "Related Properties for Sale/Rent":
 1. Submit your property at PenangPropertySale.com, it's FREE!
 (Please do not advertise your property in the comment)